Greystones Southern Access Route

PROJECT NAME: R761 to Mill Road Dual Carriageway Link Charlesland Greystones
CLIENT: Zapi Properties
CONSTRUCTION PERIOD: January 2003 to May 2004
ENGINEER: O'Connor Sutton Cronin

This project involved the construction of a link dual carriageway 2.3km long between the R761 (Kilcoole Road) and Mill Road (Greystones).

The principal elements of work included:

  • Dual carriageway with 6 No. roundabouts
  • 1.4km of single carriageway with 1 No. roundabout
  • Associated drainage and services
  • A 40 metre culvert on the Three Trout's River

Designed & maintained by Bluebloc Digital