Blessington Inner Relief Road

PROJECT NAME: Blessington Inner Relief Road - Phase 1
CLIENT: Cookehill Ltd.
CONSTRUCTION PERIOD: February 2003 to July 2004
ENGINEER: Kilgallen and Partners Consulting Engineers

This project involved 2kms of roads bypassing Blessington Main Street and proving access to a number of site developments and a new Town Centre.

The principle elements of the project included:

  • Provision of all services and utilities along the route
  • 2kms of carriageway and 3 No. roundabout